The project was built on 72 decares of land belonging to the Turkish Mothers Association and the International Lions Club, on the İzmit–Akmeşe road within the boundaries of Karaabdülbaki Village.
Site Areas
13,600 m²Construction area
58,400 m²Open area
5,400 m²Enclosed construction area
1,250 m²Social and administrative building
4,150 m²Work centers
Funding
| Total project cost | €3,000,000 |
|---|---|
| Grant secured | €1,308,000 |
| Loan required to start operations | €1,692,000 |
Timeline
| Construction start | 1 January 2005 |
|---|---|
| Construction completion | 1 September 2005 |
| Production center opening | 1 November 2005 |
Disability in Kocaeli
During the project’s preparation, the number of people with disabilities in Kocaeli was recorded as 19,494. Distribution by type of disability: